2Lesson 2 of 6 · 3 min
Post your daily update
Your HoD sees progress through your updates. Post one on each working day you work on a task. If you forget, Simple Software reminds you at 5 PM.
Step by step
- 1
Open the composer
On Today, tap Update next to the task under Updates to post. The task opens with the Update tab of its composer ready.
- 2
Set your progress
Drag the % complete slider to how complete the task is now, in steps of 5%. Be honest: it rolls up into your department's and the project's progress.
- 3
Say what you did
Write one or two lines in What did you do today?, for example "Revised experiments 1–6". Open Problems, support needed, plan for tomorrow if you need help.
- 4
Attach evidence
Tap Attach evidence to add photos, PDFs or spreadsheets, up to 25 MB each. Evidence is what NAAC and IQAC ask for later.
- 5
Post update
Tap Post update. It appears at the top of the task's updates, and the person who assigned you the task is notified.